Since the flowchart didn't produce the root cause, further analysis was done.
|
- First a checksheet was performed to help narrow down the possibilities. Enters through the exit gate were included as suggested by Kate Jones, manager River Club Apartments.
|
Checksheet |
4:00-6:00p.m. |
Summary |
# that enter through exit gate | x | x | x | x |
# of times the gate is hit by cars | x | | | |
|
- The checksheet showed that the enters through the exit might be a possible root cause, but we were not sure why.
|
- An Ishikawa Diagram was devised with the gate entry/exit process on the right to determine the exact root cause.
|
- Bulldog Consulting then asked why their are problems with the process and came up with the two branches.
|
- The suggestions resulting from the fishbone diagram would help out with the card entry system problems, so we focused our attention on the other branch.
|
- The Ishikawa Diagram showed that the root cause of this branch to be the number of cars entering through the exit gate.
|